Luas Works on Steven's Hill Dublin 8
Break line image
10  February  2004

To ask the Minister for Transport if the disruptive LUAS works are six months overdue for completion on Steven's Hill, Dublin 8; and the new deadline date for completion.

- Aengus Ó Snodaigh.
For WRITTEN answer on Tuesday, 10th February, 2004.
Ref No:   3980/04

Answered by Minister for Transport
(Séamus Brennan)

REPLY

As the Deputy is aware, the Railway Procurement Agency (RPA) is responsible for the management of the Luas project. The RPA have informed me, however, that St. Steevens Lane has now been closed permanently to through traffic following initial periods of temporary closure. They have also assured me that the closure of the Lane to through traffic is in line with the plans for Luas Line A in respect of which a Light Railway Order has been made.  The RPA have advised me that the Luas works in this area will be completed over the coming weeks when trial running will commence.